ISEB-PM1 · Question #410
What should be covered in an implementation when the change is approved? ISEB ISEB-PM1 Exam
The correct answer is D. Defect repair. In change control processes (a core ISEB PM1 topic), an approved change typically originates from an identified defect - so when the change moves into implementation, what is actually carried out is the defect repair that was scoped and authorized through the change request…
Question
What should be covered in an implementation when the change is approved? ISEB ISEB-PM1 Exam
Options
- AFunctional requirement
- BStatus report
- CCustomer need
- DDefect repair
How the community answered
(27 responses)- A4% (1)
- B15% (4)
- C7% (2)
- D74% (20)
Explanation
In change control processes (a core ISEB PM1 topic), an approved change typically originates from an identified defect - so when the change moves into implementation, what is actually carried out is the defect repair that was scoped and authorized through the change request. This ties directly to configuration management: the approved change authorizes fixing a known flaw, and implementation is where that fix is delivered.
Why the distractors are wrong:
- A. Functional requirement - Requirements are captured during planning/analysis, not enacted during an approved change implementation.
- B. Status report - A status report is a monitoring and communication output, not something "implemented" as part of a change.
- C. Customer need - Customer needs drive requirements upstream; by the implementation stage, those needs have already been translated into deliverables and change requests.
Memory tip: Think of the change control cycle as a loop - a defect is found → a change is requested → the change is approved → the defect is repaired. The word "repair" anchors the implementation step to the defect that triggered the change in the first place.