Who selects the appropriate processes for a project? ISEB ISEB-PM1 Exam

The correct answer is C. Project manager and project team. See the full explanation below for the reasoning.

Organizational Aspects of Project Management

Question

Who selects the appropriate processes for a project? ISEB ISEB-PM1 Exam

Options

  • AProject stakeholders
  • BProject sponsor and project stakeholder
  • CProject manager and project team
  • DProject manager and project sponsor

How the community answered

(37 responses)
  • A
    11% (4)
  • B
    8% (3)
  • C
    78% (29)
  • D
    3% (1)

Topics

#process selection#project manager role#project team#process groups