In which type of organization does a project manager have a moderate-to-high resource availability?

The correct answer is D. Strong. In a Strong Matrix organization, the project manager holds moderate-to-high authority and resource availability because the balance of power has shifted significantly toward the project side - dedicated project managers exist full-time and can directly assign team members…

Organizational Aspects of Project Management

Question

In which type of organization does a project manager have a moderate-to-high resource availability?

Options

  • AFunctional
  • BWeak
  • CBalanced
  • DStrong

How the community answered

(58 responses)
  • A
    3% (2)
  • B
    5% (3)
  • C
    12% (7)
  • D
    79% (46)

Explanation

In a Strong Matrix organization, the project manager holds moderate-to-high authority and resource availability because the balance of power has shifted significantly toward the project side - dedicated project managers exist full-time and can directly assign team members, unlike weaker structures where functional managers retain that control.

Why the distractors are wrong:

  • A (Functional): The functional manager has nearly all authority; the project manager role barely exists and has minimal resource control.
  • B (Weak Matrix): The PM exists but has limited influence - more of a coordinator than a decision-maker, with low resource availability.
  • C (Balanced Matrix): Power is split roughly equally between functional and project managers, giving the PM only low-to-moderate resource availability - not moderate-to-high.

Memory tip: Think of the matrix as a power dial from Functional → Weak → Balanced → Strong → Projectized. Each step right gives the PM more power. "Strong" is one notch below full projectized control, landing squarely at moderate-to-high - the sweet spot the exam loves to test.