In which type of organization does a project manager have a moderate-to-high resource availability?
The correct answer is D. Strong. In a Strong Matrix organization, the project manager holds moderate-to-high authority and resource availability because the balance of power has shifted significantly toward the project side - dedicated project managers exist full-time and can directly assign team members…
Question
In which type of organization does a project manager have a moderate-to-high resource availability?
Options
- AFunctional
- BWeak
- CBalanced
- DStrong
How the community answered
(58 responses)- A3% (2)
- B5% (3)
- C12% (7)
- D79% (46)
Explanation
In a Strong Matrix organization, the project manager holds moderate-to-high authority and resource availability because the balance of power has shifted significantly toward the project side - dedicated project managers exist full-time and can directly assign team members, unlike weaker structures where functional managers retain that control.
Why the distractors are wrong:
- A (Functional): The functional manager has nearly all authority; the project manager role barely exists and has minimal resource control.
- B (Weak Matrix): The PM exists but has limited influence - more of a coordinator than a decision-maker, with low resource availability.
- C (Balanced Matrix): Power is split roughly equally between functional and project managers, giving the PM only low-to-moderate resource availability - not moderate-to-high.
Memory tip: Think of the matrix as a power dial from Functional → Weak → Balanced → Strong → Projectized. Each step right gives the PM more power. "Strong" is one notch below full projectized control, landing squarely at moderate-to-high - the sweet spot the exam loves to test.