Which stakeholder is responsible for managing related projects in a coordinated way?

The correct answer is C. Program manager. A Program manager (C) coordinates and manages a group of related projects in a unified way to achieve benefits that couldn't be realized by managing them independently - that's the textbook definition of a program. A (Sponsor) provides funding and organizational support but…

Organizational Aspects of Project Management

Question

Which stakeholder is responsible for managing related projects in a coordinated way?

Options

  • ASponsor
  • BPortfolio manager
  • CProgram manager
  • DProject manager

How the community answered

(27 responses)
  • A
    11% (3)
  • B
    4% (1)
  • C
    81% (22)
  • D
    4% (1)

Explanation

A Program manager (C) coordinates and manages a group of related projects in a unified way to achieve benefits that couldn't be realized by managing them independently - that's the textbook definition of a program.

  • A (Sponsor) provides funding and organizational support but doesn't actively manage projects or coordinate them with each other.
  • B (Portfolio manager) oversees a collection of programs and projects chosen for strategic alignment, but focuses on selecting and prioritizing work rather than coordinating the interdependencies between related projects.
  • D (Project manager) is responsible for a single project, not a coordinated group of them.

Memory tip: Think of it as a hierarchy - Portfolio > Program > Project. The program manager sits in the middle, stitching together related projects; the portfolio manager sits above, choosing which programs and projects the organization should pursue.