ISEB-PM1 · Question #290
In which of the following organizational structures does the project manager have full authority on a project?
The correct answer is D. Projectized. In a projectized organization, the project manager has complete authority - team members report directly to them, resources are dedicated to the project, and the PM controls budget, staffing, and priorities without competing with functional managers. Why the distractors are…
Question
In which of the following organizational structures does the project manager have full authority on a project?
Options
- AFunctional
- BStrong matrix
- CBalanced matrix
- DProjectized
How the community answered
(27 responses)- A4% (1)
- B4% (1)
- C7% (2)
- D85% (23)
Explanation
In a projectized organization, the project manager has complete authority - team members report directly to them, resources are dedicated to the project, and the PM controls budget, staffing, and priorities without competing with functional managers.
Why the distractors are wrong:
- Functional (A): Authority sits with the functional manager; the project manager has little to no formal power and often acts as a coordinator.
- Strong matrix (B): The PM has more authority than the functional manager, but authority is still shared - not full or exclusive.
- Balanced matrix (C): Authority is split roughly equally between the PM and functional manager, making it a compromise structure with the most ambiguity.
Memory tip: Think of the word "projectized" as meaning the project is everything - the organization is built around projects, so naturally the project manager reigns supreme. If you can picture a dedicated project team with no other boss, that's projectized.
Topics
Community Discussion
No community discussion yet for this question.