ISEB-PM1 · Question #291
What are three basic types of project phase-to-phase relationships?
The correct answer is B. Sequential, Iterative, Overlapping. Option B is correct because the PMI/PMBOK framework defines exactly three phase-to-phase relationships: Sequential (one phase must finish before the next begins), Iterative (phases are planned one at a time, with the next phase planned based on outcomes of the current one), and…
Question
What are three basic types of project phase-to-phase relationships?
Options
- ASequential, Overlapping, Non-overlapping
- BSequential, Iterative, Overlapping
- CSequential, Non-overlapping, Iterative
- DIterative, Overlapping, Non-overlapping
How the community answered
(28 responses)- A11% (3)
- B71% (20)
- C14% (4)
- D4% (1)
Explanation
Option B is correct because the PMI/PMBOK framework defines exactly three phase-to-phase relationships: Sequential (one phase must finish before the next begins), Iterative (phases are planned one at a time, with the next phase planned based on outcomes of the current one), and Overlapping (a phase starts before the previous one finishes, sometimes called fast tracking).
Why the distractors fail: Options A and C both include "Non-overlapping" - this is not a recognized PMBOK term for a phase relationship. It's a plausible-sounding distractor, but the official taxonomy uses Iterative, not Non-overlapping, as the third type. Option D drops Sequential entirely, which is fundamental and cannot be omitted.
Memory tip: Think S-I-O - "Some Initiatives Overlap." Sequential → Iterative → Overlapping. If you see "Non-overlapping" as a choice, eliminate it immediately - it's the trap in every version of this question.
Topics
Community Discussion
No community discussion yet for this question.