Question
If you are the project manager for a new project. You have collected the necessary input information and delivered the project charter to the stakeholders. What should you do next?
Options
- ADevelop the preliminary project scope statement.
- BGet the project charter signed.
- CStart to create project plan
- DStart the initial project planning process.