ISEB-PM1 · Question #189

You are a project manager working on a software development project. You've developed the risk management plan, identified risks, and determined risk responses for the risks. One of the risks you…

The correct answer is C. Secondary risk. Secondary risk (C) is a new risk that arises as a direct result of implementing a risk response. In this scenario, you responded to the first risk, and that response itself caused a new risk to emerge - that's the defining characteristic of a secondary risk. Why the others are…

Risk Management

Question

You are a project manager working on a software development project. You've developed the risk management plan, identified risks, and determined risk responses for the risks. One of the risks you identified occurs, and you implement the response for that risk. Then, another risk occurs as a result of the response you implemented. What type of risk is this called?

Options

  • AResidual risk
  • BMitigated risk
  • CSecondary risk
  • DTrigger risk

How the community answered

(49 responses)
  • A
    8% (4)
  • B
    14% (7)
  • C
    73% (36)
  • D
    4% (2)

Explanation

Secondary risk (C) is a new risk that arises as a direct result of implementing a risk response. In this scenario, you responded to the first risk, and that response itself caused a new risk to emerge - that's the defining characteristic of a secondary risk.

Why the others are wrong:

  • A (Residual risk): A residual risk is the remaining risk left over after a response has been applied - not a new risk created by the response itself.
  • B (Mitigated risk): "Mitigated risk" isn't a standard PMI risk category; mitigation is a response strategy, not a risk type.
  • D (Trigger risk): A trigger (or risk trigger) is a warning sign or condition that indicates a risk is about to occur - it's a signal, not the resulting risk.

Memory tip: Think of secondary risks as "side effects" - just like a medication can cure one problem but cause a side effect, a risk response can solve one risk but create a secondary one. Primary response → Secondary risk.

Topics

#secondary risk#risk response#risk types#risk identification