ISEB-PM1 · Question #213
Which of the following is an example of a risk symptom?
The correct answer is A. Failure to meet intermediate milestones. Risk symptoms (also called "triggers" or "warning signs") are indirect indicators that a risk event has occurred or is about to occur. Failing to meet intermediate milestones is a classic symptom - it signals that underlying risks (resource shortages, scope creep, technical…
Question
Which of the following is an example of a risk symptom?
Options
- AFailure to meet intermediate milestones
- BForce of nature, such as a flood
- CRisk threshold target
- DCrashing front loading or fast tracking
How the community answered
(36 responses)- A72% (26)
- B8% (3)
- C3% (1)
- D17% (6)
Explanation
Risk symptoms (also called "triggers" or "warning signs") are indirect indicators that a risk event has occurred or is about to occur. Failing to meet intermediate milestones is a classic symptom - it signals that underlying risks (resource shortages, scope creep, technical blockers) may be materializing, even before the final deadline is missed.
Why the distractors are wrong:
- B (Force of nature/flood): This is a risk event itself - an actual occurrence - not a symptom that warns of risk.
- C (Risk threshold target): This is a risk management parameter used to define tolerance levels, not a symptom of risk.
- D (Crashing, front-loading, or fast tracking): These are schedule compression techniques (responses to risk), not indicators that risk is present.
Memory tip: Think of risk symptoms like a fever - the fever isn't the illness, it's the signal something is wrong. A missed milestone is the "fever" telling you a deeper project risk has flared up. Anything that responds to or defines risk (threshold, compression techniques) is not the symptom itself.