In attempting to complete the project faster, the project manager looks at the cost associated with crashing each activity. The BEST approach to crashing would also include looking at the:
The correct answer is A. Risk impact of crashing each activity. You've hit your session limit · resets 10:20pm (America/New_York)
Risk Management
Question
In attempting to complete the project faster, the project manager looks at the cost associated with crashing each activity. The BEST approach to crashing would also include looking at the:
Options
- ARisk impact of crashing each activity.
- BCustomer's opinion of which activities to crash.
- CBoss's opinion of which activities to crash and in which order.
- DProject life cycle phase in which the activity is due to occur.
How the community answered
(49 responses)- A78% (38)
- B6% (3)
- C12% (6)
- D4% (2)
Explanation
You've hit your session limit · resets 10:20pm (America/New_York)
Topics
#schedule crashing#risk impact#schedule compression#cost-risk tradeoff