ISEB-PM1 · Question #377
A risk may be graded into different priorities by which process?
The correct answer is C. Qualitative risk analysis. Qualitative Risk Analysis (C) is the process that grades or prioritizes risks by assessing their probability and impact, typically using a probability-impact matrix to rank them as high, medium, or low priority. This prioritization helps project teams focus attention on the…
Question
A risk may be graded into different priorities by which process?
Options
- ARisk monitoring and controlling
- BRisk response planning
- CQualitative risk analysis
- DQuantitative risk analysis
How the community answered
(34 responses)- A12% (4)
- B3% (1)
- C79% (27)
- D6% (2)
Explanation
Qualitative Risk Analysis (C) is the process that grades or prioritizes risks by assessing their probability and impact, typically using a probability-impact matrix to rank them as high, medium, or low priority. This prioritization helps project teams focus attention on the risks that matter most.
- A (Risk Monitoring and Controlling) is wrong because that process tracks identified risks and monitors residual risks - it occurs after risks have already been prioritized.
- B (Risk Response Planning) is wrong because it develops strategies to address risks that have already been prioritized, not the prioritization itself.
- D (Quantitative Risk Analysis) is wrong because it uses numerical methods (Monte Carlo simulations, decision trees) to quantify the numeric probability and impact of risks - it doesn't grade/prioritize them categorically.
Memory tip: Think of "Qualitative" as qualifying risks into buckets (high/medium/low), while "Quantitative" means quantity - actual numbers and probabilities. You must qualify (prioritize) before you can plan a response.