ISEB-PM1 · Question #376
When does risk monitoring and control occur?
The correct answer is C. Throughout the life of the project. Risk monitoring and control is a continuous process that spans the entire project lifecycle - from initiation through closure - because new risks can emerge at any point, and existing risks change in probability or impact as the project evolves. Why the distractors are wrong: A…
Question
When does risk monitoring and control occur?
Options
- AAt project initiation
- BDuring work performance analysis
- CThroughout the life of the project
- DAt project milestones
How the community answered
(35 responses)- A6% (2)
- B17% (6)
- C71% (25)
- D6% (2)
Explanation
Risk monitoring and control is a continuous process that spans the entire project lifecycle - from initiation through closure - because new risks can emerge at any point, and existing risks change in probability or impact as the project evolves.
Why the distractors are wrong:
- A (Project initiation): Risk identification begins at initiation, but monitoring and control can't end there - you'd be blind to risks that arise mid-project.
- B (Work performance analysis): This is one input used during risk monitoring, not the timeframe that defines when monitoring occurs.
- D (Project milestones): Checking risk only at milestones leaves long gaps of unmonitored exposure; risks don't wait for scheduled checkpoints.
Memory tip: Think of risk monitoring like a smoke detector - it doesn't run only when you first install it or only during inspections. It runs constantly, because a fire can start at any time.