When does risk monitoring and control occur?

The correct answer is C. Throughout the life of the project. Risk monitoring and control is a continuous process that spans the entire project lifecycle - from initiation through closure - because new risks can emerge at any point, and existing risks change in probability or impact as the project evolves. Why the distractors are wrong: A…

Risk Management

Question

When does risk monitoring and control occur?

Options

  • AAt project initiation
  • BDuring work performance analysis
  • CThroughout the life of the project
  • DAt project milestones

How the community answered

(35 responses)
  • A
    6% (2)
  • B
    17% (6)
  • C
    71% (25)
  • D
    6% (2)

Explanation

Risk monitoring and control is a continuous process that spans the entire project lifecycle - from initiation through closure - because new risks can emerge at any point, and existing risks change in probability or impact as the project evolves.

Why the distractors are wrong:

  • A (Project initiation): Risk identification begins at initiation, but monitoring and control can't end there - you'd be blind to risks that arise mid-project.
  • B (Work performance analysis): This is one input used during risk monitoring, not the timeframe that defines when monitoring occurs.
  • D (Project milestones): Checking risk only at milestones leaves long gaps of unmonitored exposure; risks don't wait for scheduled checkpoints.

Memory tip: Think of risk monitoring like a smoke detector - it doesn't run only when you first install it or only during inspections. It runs constantly, because a fire can start at any time.

Topics

#risk monitoring and control#project lifecycle#continuous monitoring#timing