You are assigned to implement the project control plan. What should you do to ensure the plan is effective and current? ISEB ISEB-PM1 Exam

The correct answer is A. Perform periodic project performance reviews. Performing periodic project performance reviews (A) is the correct approach because a control plan only stays effective if you continuously monitor actual progress against the plan, identify deviations, and take corrective action - that cycle of review and adjustment is what…

Project Control

Question

You are assigned to implement the project control plan. What should you do to ensure the plan is effective and current? ISEB ISEB-PM1 Exam

Options

  • APerform periodic project performance reviews.
  • BIdentify quality project standards.
  • CFollow ISO 9000 quality standards
  • DComplete the quality control checklist.

How the community answered

(42 responses)
  • A
    74% (31)
  • B
    17% (7)
  • C
    7% (3)
  • D
    2% (1)

Explanation

Performing periodic project performance reviews (A) is the correct approach because a control plan only stays effective if you continuously monitor actual progress against the plan, identify deviations, and take corrective action - that cycle of review and adjustment is what "controlling" a project means.

Why the distractors are wrong:

  • B (Identify quality standards): Identifying standards is a planning activity that happens before implementation, not a control activity during execution.
  • C (Follow ISO 9000): ISO 9000 is a general quality management framework, not a project control mechanism - applying it doesn't ensure your specific project plan stays current.
  • D (Complete a quality control checklist): A checklist is a one-time verification tool, not an ongoing review process; it doesn't give you the continuous feedback loop needed to keep a control plan effective.

Memory tip: Think of "control" as a cycle, not a one-time action - Control = Review → Compare → Correct → Repeat. Only option A describes an ongoing, repeating activity, which is the hallmark of any control process.

Topics

#project control plan#performance reviews#plan effectiveness#monitoring