ISEB-PM1 · Question #211
Which type of analysis is used to examine project results through time to determine if performance is improving or deteriorating?
The correct answer is D. Trend. Trend analysis examines project performance data over time to identify patterns - whether results are getting better or worse - making it the right tool for tracking directional movement across reporting periods. A (Control chart) is wrong: control charts monitor process…
Question
Which type of analysis is used to examine project results through time to determine if performance is improving or deteriorating?
Options
- AControl chart
- BEarned value
- CVariance
- DTrend
How the community answered
(50 responses)- A2% (1)
- B18% (9)
- C8% (4)
- D72% (36)
Explanation
Trend analysis examines project performance data over time to identify patterns - whether results are getting better or worse - making it the right tool for tracking directional movement across reporting periods.
- A (Control chart) is wrong: control charts monitor process stability and identify variation within acceptable limits, but they focus on whether a process is "in control," not on directional improvement/deterioration over time.
- B (Earned value) is wrong: earned value analysis measures cost and schedule performance at a point in time using metrics like CPI and SPI - it can feed trend analysis, but isn't itself the technique for examining results through time.
- C (Variance analysis) is wrong: variance analysis compares actual versus planned performance at a given moment, revealing how much deviation exists, not where it's heading.
Memory tip: Think "trend = trajectory." If the question uses words like over time, improving, deteriorating, or direction, the answer is always trend analysis - it's the only technique whose whole purpose is reading the arc of performance across time.
Topics
Community Discussion
No community discussion yet for this question.