ISEB-PM1 · Question #315
Which of the following is an input to the Direct and Manage Project Execution Process?
The correct answer is A. Approved corrective actions. Approved corrective actions (A) are a direct input to the Direct and Manage Project Execution process because they represent previously authorized decisions - approved through Integrated Change Control - that the team must now implement to bring performance back in line with…
Question
Which of the following is an input to the Direct and Manage Project Execution Process?
Options
- AApproved corrective actions
- BApproved contract documentation
- CWork performance information
- DRejected change requests
How the community answered
(58 responses)- A72% (42)
- B9% (5)
- C3% (2)
- D16% (9)
Explanation
Approved corrective actions (A) are a direct input to the Direct and Manage Project Execution process because they represent previously authorized decisions - approved through Integrated Change Control - that the team must now implement to bring performance back in line with the project management plan.
Option B (Approved contract documentation) is incorrect; contract documents are inputs to procurement processes, not to directing and managing project work execution.
Option C (Work performance information) is wrong because it flows the opposite direction - it is an output of Direct and Manage Project Execution, produced as the team carries out the work.
Option D (Rejected change requests) are incorrect by definition: rejected requests mean no action is authorized, so they have no role as inputs driving execution activities.
Memory tip: Think of the inputs to this process as "what you've been told to do." Approved corrective actions, preventive actions, and defect repairs all carry the word approved - they've cleared the change control gate and are now orders to execute. If it's a rejection or an output (like performance data), it doesn't feed into execution.
Topics
Community Discussion
No community discussion yet for this question.