ISEB-PM1 · Question #316
Which of the following consists of the detailed project scope statement and its associated WBS and WBS dictionary?
The correct answer is D. Scope baseline. Scope baseline (D) is the approved, formal combination of three documents: the detailed project scope statement, the Work Breakdown Structure (WBS), and the WBS dictionary. Together, these form the baseline against which scope performance and changes are measured throughout the…
Question
Which of the following consists of the detailed project scope statement and its associated WBS and WBS dictionary?
Options
- AScope plan
- BProduct scope
- CScope management plan
- DScope baseline
How the community answered
(31 responses)- A3% (1)
- B10% (3)
- C6% (2)
- D81% (25)
Explanation
Scope baseline (D) is the approved, formal combination of three documents: the detailed project scope statement, the Work Breakdown Structure (WBS), and the WBS dictionary. Together, these form the baseline against which scope performance and changes are measured throughout the project lifecycle.
Why the distractors are wrong:
- A. Scope plan - Not a recognized standalone PMBOK term; this is a distractor playing on the word "scope."
- B. Product scope - Refers to the features and functions of the product or deliverable itself, not a document package.
- C. Scope management plan - Describes how scope will be defined, validated, and controlled, but does not contain the scope statement, WBS, or WBS dictionary.
Memory tip: Think of the scope baseline as a three-legged stool - scope statement + WBS + WBS dictionary. Remove any one leg and it falls. The word baseline signals a frozen, approved reference point (like a cost baseline or schedule baseline), making D the natural answer whenever all three documents are bundled together.