ISEB-PM1 · Question #415
What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?
The correct answer is B. Rolling wave planning. Rolling wave planning (B) describes exactly this approach: near-term work is planned with high detail, while future work remains at a higher level of abstraction - then you "roll" forward as time passes, progressively elaborating future work into detailed plans. It's a core…
Question
What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?
Options
- AFinish-to-start planning
- BRolling wave planning
- CShort term planning
- DDependency determination
How the community answered
(37 responses)- A16% (6)
- B70% (26)
- C8% (3)
- D5% (2)
Explanation
Rolling wave planning (B) describes exactly this approach: near-term work is planned with high detail, while future work remains at a higher level of abstraction - then you "roll" forward as time passes, progressively elaborating future work into detailed plans. It's a core concept in iterative and agile project management.
Why the distractors fail:
- A (Finish-to-start) is a task dependency type, not a planning approach - it means one task must finish before the next can start.
- C (Short term planning) is a made-up distractor; no formal PM methodology uses this term for this concept.
- D (Dependency determination) is a process for identifying relationships between tasks, not a planning horizon strategy.
Memory tip: Picture an ocean wave - the crest (near future) is crisp and well-defined, while the water far behind it is flat and vague. As the wave rolls forward, new detail emerges at the front. That's rolling wave planning.