ISEB-PM1 · Question #415

What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?

The correct answer is B. Rolling wave planning. Rolling wave planning (B) describes exactly this approach: near-term work is planned with high detail, while future work remains at a higher level of abstraction - then you "roll" forward as time passes, progressively elaborating future work into detailed plans. It's a core…

Project Planning

Question

What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?

Options

  • AFinish-to-start planning
  • BRolling wave planning
  • CShort term planning
  • DDependency determination

How the community answered

(37 responses)
  • A
    16% (6)
  • B
    70% (26)
  • C
    8% (3)
  • D
    5% (2)

Explanation

Rolling wave planning (B) describes exactly this approach: near-term work is planned with high detail, while future work remains at a higher level of abstraction - then you "roll" forward as time passes, progressively elaborating future work into detailed plans. It's a core concept in iterative and agile project management.

Why the distractors fail:

  • A (Finish-to-start) is a task dependency type, not a planning approach - it means one task must finish before the next can start.
  • C (Short term planning) is a made-up distractor; no formal PM methodology uses this term for this concept.
  • D (Dependency determination) is a process for identifying relationships between tasks, not a planning horizon strategy.

Memory tip: Picture an ocean wave - the crest (near future) is crisp and well-defined, while the water far behind it is flat and vague. As the wave rolls forward, new detail emerges at the front. That's rolling wave planning.

Topics

#rolling wave planning#progressive elaboration#schedule planning#planning approach