BCS-ISEB
ISEB-PM1 · Question #27
Using the chart, what is the lowest cost of crashing this project to save four weeks?
The correct answer is B. $6,000. You've hit your session limit · resets 10:20pm (America/New_York)
Project Planning
Question
Using the chart, what is the lowest cost of crashing this project to save four weeks?
Options
- A$18,000
- B$6,000
- C$7,000
- D$9,000
How the community answered
(26 responses)- A4% (1)
- B77% (20)
- C8% (2)
- D12% (3)
Explanation
You've hit your session limit · resets 10:20pm (America/New_York)
Topics
#schedule crashing#cost analysis#critical path#crash cost
Community Discussion
No community discussion yet for this question.