ISEB-PM1 · Question #27

Using the chart, what is the lowest cost of crashing this project to save four weeks?

The correct answer is B. $6,000. You've hit your session limit · resets 10:20pm (America/New_York)

Project Planning

Question

Using the chart, what is the lowest cost of crashing this project to save four weeks?

Options

  • A$18,000
  • B$6,000
  • C$7,000
  • D$9,000

How the community answered

(26 responses)
  • A
    4% (1)
  • B
    77% (20)
  • C
    8% (2)
  • D
    12% (3)

Explanation

You've hit your session limit · resets 10:20pm (America/New_York)

Topics

#schedule crashing#cost analysis#critical path#crash cost