Which of the following is the correct network diagram for the table?
The correct answer is A. Begin - A - C - D - E - End - B - D. Option A correctly represents the network by showing two distinct paths: the main path (Begin → A → C → D → E → End) and a parallel branch where B feeds directly into D, matching the predecessor relationships defined in the table. This structure captures that B is an…
Question
Which of the following is the correct network diagram for the table?
Options
- ABegin - A - C - D - E - End - B - D
- BBegin - A - B - C - D - E - End
- CBegin - A - B - D - E - End A - C - D
- DBegin - A - C - D - E - End - B - C
How the community answered
(35 responses)- A71% (25)
- B9% (3)
- C17% (6)
- D3% (1)
Explanation
Option A correctly represents the network by showing two distinct paths: the main path (Begin → A → C → D → E → End) and a parallel branch where B feeds directly into D, matching the predecessor relationships defined in the table. This structure captures that B is an independent activity that merges into the network at D, not earlier.
Why the distractors fail:
- B is wrong because it forces all activities into a single sequential chain (A → B → C → D → E), ignoring that B runs in parallel and is not a predecessor of C.
- C is wrong because it incorrectly shows A splitting into both B and C as successors, misrepresenting A's role in the precedence table.
- D is wrong because it connects B into C rather than D, placing B's output at the wrong merge point in the network.
Memory tip: In network diagrams, look for where each activity merges back into the main path. The key question is: which node does the parallel branch feed into? Trace the predecessors of D - if the table shows B is a predecessor of D (not C), then B must connect directly to D, which only Option A captures correctly.