BCS-ISEB
ISEB-PM1 · Question #71
Which of the following is CORRECT?
The correct answer is A. The critical path helps prove how long the project will take. You've hit your session limit · resets 10:20pm (America/New_York)
Project Planning
Question
Which of the following is CORRECT?
Options
- AThe critical path helps prove how long the project will take.
- BThere can be only one critical path.
- CThe network diagram will change every time the end date changes.
- DA project can never have negative float.
How the community answered
(32 responses)- A84% (27)
- B3% (1)
- C3% (1)
- D9% (3)
Explanation
You've hit your session limit · resets 10:20pm (America/New_York)
Topics
#critical path method#network diagram#schedule management#float
Community Discussion
No community discussion yet for this question.