ISEB-PM1 · Question #71

Which of the following is CORRECT?

The correct answer is A. The critical path helps prove how long the project will take. You've hit your session limit · resets 10:20pm (America/New_York)

Project Planning

Question

Which of the following is CORRECT?

Options

  • AThe critical path helps prove how long the project will take.
  • BThere can be only one critical path.
  • CThe network diagram will change every time the end date changes.
  • DA project can never have negative float.

How the community answered

(32 responses)
  • A
    84% (27)
  • B
    3% (1)
  • C
    3% (1)
  • D
    9% (3)

Explanation

You've hit your session limit · resets 10:20pm (America/New_York)

Topics

#critical path method#network diagram#schedule management#float