The seller tells you that your activities have resulted in an increase in their costs. You should:

The correct answer is C. Ask the seller for supporting information. You've hit your session limit · resets 10:20pm (America/New_York)

Project Control

Question

The seller tells you that your activities have resulted in an increase in their costs. You should:

Options

  • ARecommend a change to the project costs.
  • BHave a meeting with management to find out what to do.
  • CAsk the seller for supporting information.
  • DDeny any wrongdoing.

How the community answered

(30 responses)
  • A
    10% (3)
  • B
    3% (1)
  • C
    83% (25)
  • D
    3% (1)

Explanation

You've hit your session limit · resets 10:20pm (America/New_York)

Topics

#contract claims#seller disputes#cost verification#contract administration