ISEB-PM1 · Question #72
Which of the following is CORRECT about quality improvements?
The correct answer is B. They require the preparation of change requests or the recommendation of corrective actions. ISEB ISEB-PM1 Exam
Business Concepts
Question
Which of the following is CORRECT about quality improvements?
Options
- AThey are a tool of Perform Quality Assurance and an output of Verify Scope.
- BThey require the preparation of change requests or the recommendation of corrective actions.
- CThey occur only through experience of the project manager, team, and sponsor.
- DThey are a product of cooperation between the customer and the project manager.
How the community answered
(57 responses)- A18% (10)
- B72% (41)
- C4% (2)
- D7% (4)
Explanation
ISEB ISEB-PM1 Exam
Topics
#quality management#quality assurance#corrective actions#change requests