nerdexam
BCS-ISEB

ISEB-PM1 · Question #73

A problem occurs on an activity with free float and the project manager has extended its duration. What is MOST likely to be affected?

The correct answer is B. Resource schedules. You've hit your session limit · resets 10:20pm (America/New_York)

Project Planning

Question

A problem occurs on an activity with free float and the project manager has extended its duration. What is MOST likely to be affected?

Options

  • AProject duration
  • BResource schedules
  • CProject scope management plan
  • DThe latest start for the successor activity

How the community answered

(27 responses)
  • A
    7% (2)
  • B
    78% (21)
  • C
    11% (3)
  • D
    4% (1)

Explanation

You've hit your session limit · resets 10:20pm (America/New_York)

Topics

#free float#schedule impact#activity duration#resource scheduling

Community Discussion

No community discussion yet for this question.

Full ISEB-PM1 Practice