A problem occurs on an activity with free float and the project manager has extended its duration. What is MOST likely to be affected?
The correct answer is B. Resource schedules. You've hit your session limit · resets 10:20pm (America/New_York)
Project Planning
Question
A problem occurs on an activity with free float and the project manager has extended its duration. What is MOST likely to be affected?
Options
- AProject duration
- BResource schedules
- CProject scope management plan
- DThe latest start for the successor activity
How the community answered
(27 responses)- A7% (2)
- B78% (21)
- C11% (3)
- D4% (1)
Explanation
You've hit your session limit · resets 10:20pm (America/New_York)
Topics
#free float#schedule impact#activity duration#resource scheduling