Which of the following is NOT a reason to measure variances from the baseline?
The correct answer is D. To create a project control system. You've hit your session limit · resets 10:20pm (America/New_York)
Project Control
Question
Which of the following is NOT a reason to measure variances from the baseline?
Options
- ATo catch deviations early
- BTo allow early corrective action
- CTo determine if there are any wild fluctuations
- DTo create a project control system
How the community answered
(48 responses)- A6% (3)
- B10% (5)
- C2% (1)
- D81% (39)
Explanation
You've hit your session limit · resets 10:20pm (America/New_York)
Topics
#baseline variance#cost control#performance measurement#project monitoring