ISEB-PM1 · Question #75

A team member notifies the project manager that the activities comprising a work package are no longer appropriate. It would be BEST for the project manager to be in what part of the project…

The correct answer is C. Monitoring and controlling. You've hit your session limit · resets 10:20pm (America/New_York)

Project Control

Question

A team member notifies the project manager that the activities comprising a work package are no longer appropriate. It would be BEST for the project manager to be in what part of the project management process?

Options

  • ACorrective action
  • BIntegrated change control
  • CMonitoring and controlling
  • DProject closing

How the community answered

(50 responses)
  • A
    16% (8)
  • B
    8% (4)
  • C
    72% (36)
  • D
    4% (2)

Explanation

You've hit your session limit · resets 10:20pm (America/New_York)

Topics

#work package#integrated change control#monitoring and controlling#scope management

Community Discussion

No community discussion yet for this question.