During project executing, a project team member informs the project manager that a work package has not met the quality metric, and that she believes it is not possible to meet it. The project…

The correct answer is C. Perform Quality Control. You've hit your session limit · resets 10:20pm (America/New_York)

Quality Management

Question

During project executing, a project team member informs the project manager that a work package has not met the quality metric, and that she believes it is not possible to meet it. The project manager meets with all parties concerned to analyze the situation. Which part of the quality management process is the project manager involved in?

Options

  • APerform Quality Assurance
  • BProject Control
  • CPerform Quality Control
  • DPlan Quality

How the community answered

(20 responses)
  • A
    5% (1)
  • B
    10% (2)
  • C
    80% (16)
  • D
    5% (1)

Explanation

You've hit your session limit · resets 10:20pm (America/New_York)

Topics

#quality control#quality metrics#perform quality control#defect analysis