ISEB-PM1 · Question #513
ISEB ISEB-PM1 Exam Which tool and technique of quality planning involves comparing actual or planned practices to those of other projects to generate ideas for improvement and provide a basis by…
The correct answer is C. Benchmarking. Benchmarking is correct because it is specifically defined as comparing actual or planned practices against those of other projects (or organizations) to identify improvement ideas and establish performance baselines - exactly what the question describes. Why the distractors…
Question
ISEB ISEB-PM1 Exam Which tool and technique of quality planning involves comparing actual or planned practices to those of other projects to generate ideas for improvement and provide a basis by which to measure performance?
Options
- AHistogram
- BQuality audits
- CBenchmarking
- DPerformance measurement analysis
How the community answered
(45 responses)- A13% (6)
- B2% (1)
- C80% (36)
- D4% (2)
Explanation
Benchmarking is correct because it is specifically defined as comparing actual or planned practices against those of other projects (or organizations) to identify improvement ideas and establish performance baselines - exactly what the question describes.
Why the distractors are wrong:
- A. Histogram - a bar chart used to display frequency distributions of data; it's a quality control tool, not a comparison technique.
- B. Quality audits - a structured review to determine whether project activities comply with defined processes; it looks inward at compliance, not outward at other projects.
- D. Performance measurement analysis - not a standard PMBOK/ISEB-named quality planning technique; it conflates measurement with the comparative practice described.
Memory tip: Think of benchmarking like an athlete watching competitors to set a personal best target - you're looking outside your own project to find the mark (benchmark) you want to hit.