ISEB-PM1 · Question #43

Management wants to be sure that the project is following defined quality standards. Which of the following should they look at?

The correct answer is D. Quality audit. You've hit your session limit · resets 10:20pm (America/New_York)

Quality Management

Question

Management wants to be sure that the project is following defined quality standards. Which of the following should they look at?

Options

  • ARisk management plan
  • BWBS
  • CStatement of work
  • DQuality audit

How the community answered

(31 responses)
  • A
    10% (3)
  • B
    6% (2)
  • C
    3% (1)
  • D
    81% (25)

Explanation

You've hit your session limit · resets 10:20pm (America/New_York)

Topics

#quality audit#quality standards#quality assurance#monitoring