ISEB-PM1 · Question #43
Management wants to be sure that the project is following defined quality standards. Which of the following should they look at?
The correct answer is D. Quality audit. You've hit your session limit · resets 10:20pm (America/New_York)
Quality Management
Question
Management wants to be sure that the project is following defined quality standards. Which of the following should they look at?
Options
- ARisk management plan
- BWBS
- CStatement of work
- DQuality audit
How the community answered
(31 responses)- A10% (3)
- B6% (2)
- C3% (1)
- D81% (25)
Explanation
You've hit your session limit · resets 10:20pm (America/New_York)
Topics
#quality audit#quality standards#quality assurance#monitoring