A quality control manager decides to increase his daily sample size from three to six. The size of the control band will:

The correct answer is C. decrease. You've hit your weekly limit · resets 5am (America/New_York)

Quality Management

Question

A quality control manager decides to increase his daily sample size from three to six. The size of the control band will:

Options

  • Anot determinable from given data
  • BNone of the other alternatives apply.
  • Cdecrease
  • Dremain unchanged
  • Eincrease

How the community answered

(46 responses)
  • B
    9% (4)
  • C
    85% (39)
  • D
    2% (1)
  • E
    4% (2)

Explanation

You've hit your weekly limit · resets 5am (America/New_York)

Topics

#control charts#sample size#statistical process control#control band