Which of the following helps a project manager determine possible causes of problems on a project?

The correct answer is B. A fishbone diagram. You've hit your session limit · resets 10:20pm (America/New_York)

Quality Management

Question

Which of the following helps a project manager determine possible causes of problems on a project?

Options

  • AThe 50/50 rule
  • BA fishbone diagram
  • CA control chart
  • DA Pareto chart

How the community answered

(34 responses)
  • A
    15% (5)
  • B
    74% (25)
  • C
    9% (3)
  • D
    3% (1)

Explanation

You've hit your session limit · resets 10:20pm (America/New_York)

Topics

#fishbone diagram#cause and effect#root cause analysis#quality tools