ISEB-PM1 · Question #413
Which of the following is a tool and technique for activity duration estimating?
The correct answer is A. Parametric estimating. Parametric estimating is a recognized tool and technique for activity duration estimating (per the PMBOK Guide), using statistical relationships between historical data and variables to calculate duration - for example, multiplying the number of units by a known productivity…
Question
Which of the following is a tool and technique for activity duration estimating?
Options
- AParametric estimating
- BMonte Carlo analysis
- CTop-down estimating
- DBottom-up estimating
How the community answered
(34 responses)- A76% (26)
- B3% (1)
- C6% (2)
- D15% (5)
Explanation
Parametric estimating is a recognized tool and technique for activity duration estimating (per the PMBOK Guide), using statistical relationships between historical data and variables to calculate duration - for example, multiplying the number of units by a known productivity rate.
Why the distractors are wrong:
- B. Monte Carlo analysis is a simulation technique used for risk analysis and schedule modeling, not a primary estimating method.
- C. Top-down estimating is an analogous (high-level) estimating approach applied at the project or phase level, not a formal PMBOK-named technique for activity duration specifically - it's a description of analogous estimating, not a distinct tool.
- D. Bottom-up estimating is a tool for activity cost estimating and work package effort estimation, not specifically classified under activity duration estimating in the PMBOK framework.
Memory tip: Think "Para-metric = Para-meter = Measure with a parameter." If you have a rate (hours/unit, cost/meter), you're using parametric estimating - it's data-driven and precise, making it the go-to duration estimating technique on the exam.
Topics