nerdexam
BCS-ISEB

ISEB-PM1 · Question #413

Which of the following is a tool and technique for activity duration estimating?

The correct answer is A. Parametric estimating. Parametric estimating is a recognized tool and technique for activity duration estimating (per the PMBOK Guide), using statistical relationships between historical data and variables to calculate duration - for example, multiplying the number of units by a known productivity…

Project Planning

Question

Which of the following is a tool and technique for activity duration estimating?

Options

  • AParametric estimating
  • BMonte Carlo analysis
  • CTop-down estimating
  • DBottom-up estimating

How the community answered

(34 responses)
  • A
    76% (26)
  • B
    3% (1)
  • C
    6% (2)
  • D
    15% (5)

Explanation

Parametric estimating is a recognized tool and technique for activity duration estimating (per the PMBOK Guide), using statistical relationships between historical data and variables to calculate duration - for example, multiplying the number of units by a known productivity rate.

Why the distractors are wrong:

  • B. Monte Carlo analysis is a simulation technique used for risk analysis and schedule modeling, not a primary estimating method.
  • C. Top-down estimating is an analogous (high-level) estimating approach applied at the project or phase level, not a formal PMBOK-named technique for activity duration specifically - it's a description of analogous estimating, not a distinct tool.
  • D. Bottom-up estimating is a tool for activity cost estimating and work package effort estimation, not specifically classified under activity duration estimating in the PMBOK framework.

Memory tip: Think "Para-metric = Para-meter = Measure with a parameter." If you have a rate (hours/unit, cost/meter), you're using parametric estimating - it's data-driven and precise, making it the go-to duration estimating technique on the exam.

Topics

#activity duration estimating#parametric estimating#schedule tools#estimation techniques

Community Discussion

No community discussion yet for this question.

Full ISEB-PM1 Practice