Which process involves identifying and documenting the logical relationships among schedule activities?

The correct answer is B. Activity sequencing. Activity sequencing (B) is correct because it is the specific process of reviewing activities and determining the order in which they must occur, then documenting those dependencies (finish-to-start, start-to-start, etc.) in a network diagram or similar output. Why the others…

Project Planning

Question

Which process involves identifying and documenting the logical relationships among schedule activities?

Options

  • ASchedule development
  • BActivity sequencing
  • CCreate WBS
  • DApplying leads and lags

How the community answered

(18 responses)
  • A
    11% (2)
  • B
    83% (15)
  • D
    6% (1)

Explanation

Activity sequencing (B) is correct because it is the specific process of reviewing activities and determining the order in which they must occur, then documenting those dependencies (finish-to-start, start-to-start, etc.) in a network diagram or similar output.

Why the others are wrong:

  • A (Schedule development) comes after sequencing - it uses the relationships already identified to calculate start/end dates and produce the actual schedule.
  • C (Create WBS) breaks the project scope into deliverables and work packages, not activity relationships - it happens before sequencing.
  • D (Applying leads and lags) is a technique used within activity sequencing, not the process itself - leads and lags fine-tune existing relationships rather than identify them.

Memory tip: Think of it in order - you define activities, then you sequence them (establish logical relationships), then you develop the schedule. "Sequencing = sorting the order" - just like sorting cards in a hand before playing them.

Topics

#activity sequencing#logical relationships#schedule activities#network diagram