Which process involves aggregating the estimated costs of the individual schedule activities or work packages?

The correct answer is D. Cost budgeting. Cost Budgeting (D) is correct because it is the process of aggregating the estimated costs of individual schedule activities or work packages to establish an authorized cost baseline - this is the definition straight from the PMBOK Guide. A (Cost Baseline) is wrong because it's…

Project Planning

Question

Which process involves aggregating the estimated costs of the individual schedule activities or work packages?

Options

  • ACost baseline
  • BCost forecasting
  • CCost variance
  • DCost budgeting

How the community answered

(26 responses)
  • A
    8% (2)
  • B
    4% (1)
  • C
    12% (3)
  • D
    77% (20)

Explanation

Cost Budgeting (D) is correct because it is the process of aggregating the estimated costs of individual schedule activities or work packages to establish an authorized cost baseline - this is the definition straight from the PMBOK Guide.

  • A (Cost Baseline) is wrong because it's the output of cost budgeting, not the process itself - it's the time-phased budget used to measure and monitor cost performance.
  • B (Cost Forecasting) is wrong because forecasting projects future costs based on current performance data (like EAC - Estimate at Completion), not aggregating original estimates.
  • C (Cost Variance) is wrong because it's a performance measurement (CV = EV − AC) that tells you how much over or under budget you are, not a process for building the budget.

Memory tip: Think of the word "budget" literally - when you make a household budget, you add up (aggregate) all your individual expenses. Cost Budgeting does exactly that: it rolls up the individual estimates into one total. The word "aggregating" in the question is your direct signal to pick Budgeting.

Topics

#cost budgeting#cost aggregation#work packages#schedule activities