ISEB-PM1 · Question #496

If a project manager is concerned with gathering, integrating, and disseminating the outputs of all project management processes, she should concentrate on creating a better:

The correct answer is C. Project management information system. A Project Management Information System (PMIS) is specifically designed to gather, integrate, and disseminate information across all project management processes - making it the direct answer. It serves as the central hub for collecting inputs, processing data, and distributing…

Communication Management

Question

If a project manager is concerned with gathering, integrating, and disseminating the outputs of all project management processes, she should concentrate on creating a better:

Options

  • AWBS.
  • BCommunications management plan.
  • CProject management information system.
  • DProject scope management plan.

How the community answered

(24 responses)
  • A
    8% (2)
  • B
    4% (1)
  • C
    75% (18)
  • D
    13% (3)

Explanation

A Project Management Information System (PMIS) is specifically designed to gather, integrate, and disseminate information across all project management processes - making it the direct answer. It serves as the central hub for collecting inputs, processing data, and distributing outputs (schedules, reports, performance data) to stakeholders.

Why the distractors are wrong:

  • A. WBS - A Work Breakdown Structure organizes project scope into deliverables; it doesn't handle information flow across processes.
  • B. Communications management plan - This plan defines who gets information and how, but it doesn't gather or integrate process outputs - it relies on the PMIS to do that.
  • D. Project scope management plan - This governs how scope is defined and controlled, not how project-wide information is collected and shared.

Memory tip: Think of PMIS as the project's "nervous system" - it collects signals (inputs), processes them (integration), and sends messages throughout the body (dissemination). Any question about system-wide information flow across processes points to PMIS, not a plan or a structure.

Topics

#communications management#PMIS#information distribution#project outputs

Community Discussion

No community discussion yet for this question.