ISEB ISEB-PM1 Exam Formal written correspondence with the customer is required when:
The correct answer is B. The customer requests additional work not covered under contract. You've hit your session limit · resets 10:20pm (America/New_York)
Communication Management
Question
ISEB ISEB-PM1 Exam Formal written correspondence with the customer is required when:
Options
- ADefects are detected.
- BThe customer requests additional work not covered under contract.
- CThe project has a schedule slippage that includes changes to the critical path.
- DThe project has cost overruns.
How the community answered
(24 responses)- A8% (2)
- B71% (17)
- C4% (1)
- D17% (4)
Explanation
You've hit your session limit · resets 10:20pm (America/New_York)
Topics
#formal communication#contract changes#written correspondence#scope changes