ISEB ISEB-PM1 Exam Formal written correspondence with the customer is required when:

The correct answer is B. The customer requests additional work not covered under contract. You've hit your session limit · resets 10:20pm (America/New_York)

Communication Management

Question

ISEB ISEB-PM1 Exam Formal written correspondence with the customer is required when:

Options

  • ADefects are detected.
  • BThe customer requests additional work not covered under contract.
  • CThe project has a schedule slippage that includes changes to the critical path.
  • DThe project has cost overruns.

How the community answered

(24 responses)
  • A
    8% (2)
  • B
    71% (17)
  • C
    4% (1)
  • D
    17% (4)

Explanation

You've hit your session limit · resets 10:20pm (America/New_York)

Topics

#formal communication#contract changes#written correspondence#scope changes