As the project manager, you are preparing your methods for quality management. You are looking for a method that can demonstrate the relationship between events and their resulting effects. You want…

The correct answer is C. Ishikawa diagram. You've hit your session limit · resets 10:20pm (America/New_York)

Quality Management

Question

As the project manager, you are preparing your methods for quality management. You are looking for a method that can demonstrate the relationship between events and their resulting effects. You want to use a method to depict the events that cause a negative effect on quality. Which of the following is the BEST choice for accomplishing your objective?

Options

  • AHistogram
  • BPareto chart
  • CIshikawa diagram
  • DControl chart

How the community answered

(26 responses)
  • A
    15% (4)
  • B
    4% (1)
  • C
    73% (19)
  • D
    8% (2)

Explanation

You've hit your session limit · resets 10:20pm (America/New_York)

Topics

#Ishikawa diagram#cause and effect#quality tools#root cause analysis