nerdexam
BCS-ISEB

ISEB-PM1 · Question #53

While creating the agenda for a status meeting with the team, a project manager receives input from one team member that an item should be added. Another team member says the team is not ready to…

The correct answer is A. Compromise. You've hit your session limit · resets 10:20pm (America/New_York)

Resource Management

Question

While creating the agenda for a status meeting with the team, a project manager receives input from one team member that an item should be added. Another team member says the team is not ready to resolve the item during the meeting. After much discussion, the project manager decides to put the item on the agenda as an initial discussion item only. Which conflict resolution technique is the project manager using?

Options

  • ACompromise
  • BSmoothing
  • CForcing
  • DWithdrawal

How the community answered

(62 responses)
  • A
    74% (46)
  • B
    13% (8)
  • C
    8% (5)
  • D
    5% (3)

Explanation

You've hit your session limit · resets 10:20pm (America/New_York)

Topics

#compromise#conflict resolution techniques#negotiation#team management

Community Discussion

No community discussion yet for this question.

Full ISEB-PM1 Practice