Stakeholder analysis identifies what information and relates it to the purpose of the project?

The correct answer is D. Interest, expectations, and influence. D is correct because stakeholder analysis is fundamentally about understanding who stakeholders are in relation to the project - what they care about (interest), what they anticipate (expectations), and how much power they hold (influence). These three dimensions together allow…

Communication Management

Question

Stakeholder analysis identifies what information and relates it to the purpose of the project?

Options

  • ARequirements, influence, and functional department
  • BInterest, requirements, and functional role
  • CRequirements, expectations, and influence
  • DInterest, expectations, and influence

How the community answered

(40 responses)
  • A
    3% (1)
  • B
    5% (2)
  • C
    15% (6)
  • D
    78% (31)

Explanation

D is correct because stakeholder analysis is fundamentally about understanding who stakeholders are in relation to the project - what they care about (interest), what they anticipate (expectations), and how much power they hold (influence). These three dimensions together allow a project manager to prioritize engagement and tailor communication strategies.

Why the distractors fail:

  • A includes "functional department," which describes where a stakeholder sits organizationally - a classification attribute, not an analytical dimension tied to project purpose.
  • B includes "requirements," which are an output of stakeholder analysis (what stakeholders need), not one of the characterizing inputs used to analyze them.
  • C also includes "requirements" for the same reason - requirements are derived from the analysis, not part of what the analysis measures about stakeholders.

Memory tip: Think I.E.I. - Interest (do they care?), Expectations (what do they want to happen?), Influence (can they affect the project?). Requirements are what you produce from the analysis - they come after, not during, the stakeholder identification phase.