ISEB-PM1 · Question #362
What information does the stakeholder register contain?
The correct answer is B. Identification information. Identification information (B) is correct because the stakeholder register is a project document that records details about identified stakeholders - including their names, roles, contact information, interests, influence levels, and engagement classifications. It is…
Question
What information does the stakeholder register contain?
Options
- ACommunication model
- BIdentification information
- CCommunication method
- DIdentification plan
How the community answered
(27 responses)- A4% (1)
- B78% (21)
- C11% (3)
- D7% (2)
Explanation
Identification information (B) is correct because the stakeholder register is a project document that records details about identified stakeholders - including their names, roles, contact information, interests, influence levels, and engagement classifications. It is essentially a database of who the stakeholders are.
The distractors all belong to a different document - the Communications Management Plan: a communication model (A) describes how information flows between sender and receiver, a communication method (C) refers to channels like meetings or email, and an identification plan (D) is not a standard PMI artifact but loosely relates to planning processes, not the register itself.
Memory tip: Think of a "register" like a hotel guest register - it records who is there (identification info), not how you'll talk to them. Anything about how you communicate belongs in the Communications Plan.