What information does the stakeholder register contain?

The correct answer is B. Identification information. Identification information (B) is correct because the stakeholder register is a project document that records details about identified stakeholders - including their names, roles, contact information, interests, influence levels, and engagement classifications. It is…

Communication Management

Question

What information does the stakeholder register contain?

Options

  • ACommunication model
  • BIdentification information
  • CCommunication method
  • DIdentification plan

How the community answered

(27 responses)
  • A
    4% (1)
  • B
    78% (21)
  • C
    11% (3)
  • D
    7% (2)

Explanation

Identification information (B) is correct because the stakeholder register is a project document that records details about identified stakeholders - including their names, roles, contact information, interests, influence levels, and engagement classifications. It is essentially a database of who the stakeholders are.

The distractors all belong to a different document - the Communications Management Plan: a communication model (A) describes how information flows between sender and receiver, a communication method (C) refers to channels like meetings or email, and an identification plan (D) is not a standard PMI artifact but loosely relates to planning processes, not the register itself.

Memory tip: Think of a "register" like a hotel guest register - it records who is there (identification info), not how you'll talk to them. Anything about how you communicate belongs in the Communications Plan.