ISEB-PM1 · Question #460

What happens to a stakeholder's project influence over time?

The correct answer is B. Decreases. ISEB ISEB-PM1 Exam

Communication Management

Question

What happens to a stakeholder's project influence over time?

Options

  • AIncreases
  • BDecreases
  • CStays the same.
  • DHas no bearing.

How the community answered

(36 responses)
  • A
    6% (2)
  • B
    83% (30)
  • C
    8% (3)
  • D
    3% (1)

Explanation

ISEB ISEB-PM1 Exam

Topics

#stakeholder influence#stakeholder management#project lifecycle#stakeholder engagement