ISEB-PM1 · Question #412

What document should be reviewed by a project manager before finalizing the project closure?

The correct answer is A. Customer acceptance. Customer acceptance (A) is correct because it confirms the client has formally acknowledged that all deliverables meet the agreed-upon requirements - without this sign-off, the project cannot be legitimately closed, as acceptance is the contractual validation that the work is…

The Project Management Lifecycle

Question

What document should be reviewed by a project manager before finalizing the project closure?

Options

  • ACustomer acceptance
  • BStatement of work
  • CProduct report
  • DUser manual

How the community answered

(31 responses)
  • A
    71% (22)
  • B
    3% (1)
  • C
    10% (3)
  • D
    16% (5)

Explanation

Customer acceptance (A) is correct because it confirms the client has formally acknowledged that all deliverables meet the agreed-upon requirements - without this sign-off, the project cannot be legitimately closed, as acceptance is the contractual validation that the work is done.

Statement of work (B) is a planning document used at the start of a project to define scope, deliverables, and timelines - it's an input to the project, not a closure artifact.

Product report (C) may summarize project outputs but is not a standard, binding closure document; it doesn't represent formal stakeholder sign-off.

User manual (D) is a deliverable within the project, not a document reviewed to close it - handing it over may be part of closure, but reviewing it doesn't validate project completion.

Memory tip: Think of closure as needing a signature - Customer Acceptance is the document with the client's stamp of approval, making "A" the answer whenever the question is about finalizing or formally closing a project.

Topics

#project closure#customer acceptance#formal acceptance#closure documentation

Community Discussion

No community discussion yet for this question.