The following reports are normally developed during the project closure phase?

The correct answer is D. Records Archive, Closure Report, lessons learned & Formal Acceptance Report. You've hit your weekly limit · resets 5am (America/New_York)

The Project Management Lifecycle

Question

The following reports are normally developed during the project closure phase?

Options

  • ANone of the other alternatives apply
  • BCommunications Management Plan and Lessons Learned
  • CRecords Archive, Closure Report, & Specifications Document
  • DRecords Archive, Closure Report, lessons learned & Formal Acceptance Report
  • ECommunications Management Plan and Closure report

How the community answered

(38 responses)
  • A
    3% (1)
  • B
    16% (6)
  • C
    8% (3)
  • D
    71% (27)
  • E
    3% (1)

Explanation

You've hit your weekly limit · resets 5am (America/New_York)

Topics

#project closure#lessons learned#closure report#formal acceptance