ISEB-PM1 · Question #587
The following reports are normally developed during the project closure phase?
The correct answer is D. Records Archive, Closure Report, lessons learned & Formal Acceptance Report. You've hit your weekly limit · resets 5am (America/New_York)
The Project Management Lifecycle
Question
The following reports are normally developed during the project closure phase?
Options
- ANone of the other alternatives apply
- BCommunications Management Plan and Lessons Learned
- CRecords Archive, Closure Report, & Specifications Document
- DRecords Archive, Closure Report, lessons learned & Formal Acceptance Report
- ECommunications Management Plan and Closure report
How the community answered
(38 responses)- A3% (1)
- B16% (6)
- C8% (3)
- D71% (27)
- E3% (1)
Explanation
You've hit your weekly limit · resets 5am (America/New_York)
Topics
#project closure#lessons learned#closure report#formal acceptance