ISEB-PM1 · Question #399
Final product transition is an output of which process?
The correct answer is B. Close Project or Phase. Close Project or Phase (B) produces the final product transition because this process formally hands over the completed deliverable to the customer, operations team, or next phase - along with the transfer documentation, lessons learned, and formal acceptance. It's the…
Question
Final product transition is an output of which process?
Options
- ADirect and Manage Project Execution
- BClose Project or Phase
- CPerform Integrated Change Control
- DMonitor and Control Project Work
How the community answered
(32 responses)- A16% (5)
- B72% (23)
- C9% (3)
- D3% (1)
Explanation
Close Project or Phase (B) produces the final product transition because this process formally hands over the completed deliverable to the customer, operations team, or next phase - along with the transfer documentation, lessons learned, and formal acceptance. It's the definitive endpoint where the project's output leaves the project team's hands.
Why the distractors are wrong:
- A (Direct and Manage Project Execution): This process creates work results and deliverables, but doesn't formally transfer them - it's the doing, not the closing.
- C (Perform Integrated Change Control): This reviews and approves/rejects change requests; it has no hand in handing over a finished product.
- D (Monitor and Control Project Work): This tracks performance and reports status throughout the project lifecycle - observing progress, not concluding it.
Memory tip: Think of "Close" as the handshake - you've built the product (Execute), watched it (Monitor), adjusted it (Change Control), and now you hand it off (Close). Only a closing handshake produces a transition.