ISEB-PM1 · Question #299
Which process group can be performed outside the project's scope of control?
The correct answer is D. Initiating. ISEB ISEB-PM1 Exam
The Project Management Lifecycle
Question
Which process group can be performed outside the project's scope of control?
Options
- APlanning
- BMonitoring and Control
- CClosing
- DInitiating
How the community answered
(55 responses)- A7% (4)
- B4% (2)
- C13% (7)
- D76% (42)
Explanation
ISEB ISEB-PM1 Exam
Topics
#process groups#initiating#project lifecycle#scope of control