Which process group can be performed outside the project's scope of control?

The correct answer is D. Initiating. ISEB ISEB-PM1 Exam

The Project Management Lifecycle

Question

Which process group can be performed outside the project's scope of control?

Options

  • APlanning
  • BMonitoring and Control
  • CClosing
  • DInitiating

How the community answered

(55 responses)
  • A
    7% (4)
  • B
    4% (2)
  • C
    13% (7)
  • D
    76% (42)

Explanation

ISEB ISEB-PM1 Exam

Topics

#process groups#initiating#project lifecycle#scope of control