BCS-ISEB
ISEB-PM1 · Question #300
The procurement document is an input to which of the following processes?
The correct answer is C. Identify Stakeholders. See the full explanation below for the reasoning.
Communication Management
Question
The procurement document is an input to which of the following processes?
Options
- ADevelop Project Management Plan
- BDevelop Schedule
- CIdentify Stakeholders
- DDetermine Budget
How the community answered
(34 responses)- A6% (2)
- B3% (1)
- C76% (26)
- D15% (5)
Topics
#procurement documents#identify stakeholders#process inputs#stakeholder management
Community Discussion
No community discussion yet for this question.