ISEB-PM1 · Question #300

The procurement document is an input to which of the following processes?

The correct answer is C. Identify Stakeholders. See the full explanation below for the reasoning.

Communication Management

Question

The procurement document is an input to which of the following processes?

Options

  • ADevelop Project Management Plan
  • BDevelop Schedule
  • CIdentify Stakeholders
  • DDetermine Budget

How the community answered

(34 responses)
  • A
    6% (2)
  • B
    3% (1)
  • C
    76% (26)
  • D
    15% (5)

Topics

#procurement documents#identify stakeholders#process inputs#stakeholder management

Community Discussion

No community discussion yet for this question.