ISEB-PM1 · Question #301
Which of the following is involved in the initiation process group?
The correct answer is B. Identify Stakeholders. See the full explanation below for the reasoning.
The Project Management Lifecycle
Question
Which of the following is involved in the initiation process group?
Options
- ADevelop Project Management Plan
- BIdentify Stakeholders
- CPlan Communications
- DCollect Requirements
How the community answered
(21 responses)- A10% (2)
- B76% (16)
- C10% (2)
- D5% (1)
Topics
#initiation process group#identify stakeholders#process groups#project lifecycle