Earned value measurement is an example of:

The correct answer is A. Performance reporting. ISEB ISEB-PM1 Exam

Business Concepts

Question

Earned value measurement is an example of:

Options

  • APerformance reporting.
  • BPlanning control.
  • CIshikawa diagrams.
  • DIntegrating the project components into a whole.

How the community answered

(28 responses)
  • A
    79% (22)
  • B
    4% (1)
  • C
    7% (2)
  • D
    11% (3)

Explanation

ISEB ISEB-PM1 Exam

Topics

#earned value management#performance reporting#project metrics