ISEB-PM1 · Question #38
A project manager and team from a firm that designs railroad equipment are tasked to design a machine to load stone onto railroad cars. The design allows for two percent spillage, amounting to over…
The correct answer is A. Quality management plan. You've hit your session limit · resets 10:20pm (America/New_York)
Quality Management
Question
A project manager and team from a firm that designs railroad equipment are tasked to design a machine to load stone onto railroad cars. The design allows for two percent spillage, amounting to over two tons of spilled rock per day. In which of the following does the project manager document quality control, quality assurance, and quality improvements for this project?
Options
- AQuality management plan
- BQuality policy
- CControl charts
- DProject management plan
How the community answered
(30 responses)- A77% (23)
- B7% (2)
- C13% (4)
- D3% (1)
Explanation
You've hit your session limit · resets 10:20pm (America/New_York)
Topics
#quality management plan#quality control#quality assurance#quality documentation