Question

You are a project manager for Giraffe Enterprises. You've recently taken over for a project manager who lied about his PMI certification and was subsequently fired. Unfortunately, he did a poor job of scope definition. Which of the following could happen if you don't correct this?

Options

  • AThe project costs could increase, there might be rework, and schedule delays might result.
  • BThe project management plan's process for verification and acceptance of the deliverables
  • CThe poor scope definition will adversely affect the creation of the work breakdown structure,
  • DThe stakeholders will require overtime from the project team to keep the project on schedule.