ISEB-PM1 · Question #195
Which performance measurement tells you what the projected total cost of the project will be at completion?
The correct answer is C. EAC. ISEB ISEB-PM1 Exam
Business Concepts
Question
Which performance measurement tells you what the projected total cost of the project will be at completion?
Options
- AETC
- BCPI
- CEAC
- DSPI
How the community answered
(18 responses)- A6% (1)
- B6% (1)
- C72% (13)
- D17% (3)
Explanation
ISEB ISEB-PM1 Exam
Topics
#earned value#EAC#cost performance#project forecasting